SCOTIA-GLENVILLE CENTRAL SCHOOL DISTRICT

DISTRICT OFFICE

 

FACILITIES ADVISORY COMMITTEE MEETING MINUTES Ð APRIL 27, 2004

Committee Members Present:

 

Tom Bried                 John Geniti               Ron Hutchins           Karen Pelletier

Lynda Castronovo   James Hale              Kris Kastberg           Ann Peluso

Neal Cummings      Bob Hanlon              Randy Lombardo    Jim Rodecker

Kim DeCorah           Roger Harrison        Nick Macherone       Dawn Scagnelli

Susan Fitting                        Eric Holm                  Dave Moehle            Lauren Swift

                                                                                                            John Wisniewski

 

1.    Randy Lombardo, chairperson, welcomed everyone and called meeting to order.

 

2.    Reviewed revised Sacandaga Elementary list.

 

3.   Minutes of meeting of April 6, 2004 meeting.  Moved to accept by Susan Fitting.

      Second by Kim DeCorah.

 

4.   Discussion of maintenance issues vs. bond issues.  Agreed to create 2 sets of recommendations per school to board.

 

5.   Include in recommendation to board to allow 1% of budget every year for general upkeep.

 

6.   Items that are aidable (direct dollars from State) this year may or may not be available in future years. Committee and board need to be cognizant of this.

 

7.   Sacandaga School discussion:  Consider putting concrete in basement (possible health issues with dirt floor).  Concrete floor in basement was cut from past building project because of cost; New windows should be considered (this is not unique to Sacandaga);  Need turn around area in parking lot for buses.  Current situation of buses in street unacceptable;  General note of committee: Sacandaga School is being taken care of well. 

 

8.   Linda Castronovo reviewed the list of proposed renovations for the High School.  Strike Òexpand guidance areaÓ from list.  Add Òconsider removing porticoÓ (overhang by bus stop in front of building).  Ms. Castronovo then conducted a tour of the building

 

Future meeting dates:

 

May 4              Bus Garage then Glendaal Ð Tour and discussion Ð Meet at Bus Garage

May 25           Glen Worden Ð Tour and discussion Ð Meet in Library Media Center

June 1            High School Fields, Tennis Courts, and Finish at Lincoln

June 15         District Office and other fields

July 6

July 20                                                                                               ECH: